Z2NZ--659-24-203: Extend Chilled Water to Hospice and Audiology
Subject: Statement of Work: Install Chill Water Lines to Hospice and Audiology Location: Campus Project #: 659-24-203 Date: 26 February 2026 STATEMENT OF WORK Mechanical General: The project involves providing chilled Water from Building 31 primary chiller to serve Buildings 42 and 43. This project should be completed in 365 days and include a 1-year warranty on all items. Background Information: Building 42 and Building 43 are on separate systems, the VA wants them on the same system as Building 31. SCOPE OF WORK: Provide chilled water from the building 31 primary chiller to serve Buildings 42 and 43, bypassing the existing chillers in 42 and 43 during normal operation. Normal Operation (Primary from Building 31) Building 42 and Building 43 are served directly from building 31 chilled-water plant. The existing chillers for 42 and 43 are isolated and not in use. Valves and actuators shall be connected to the Building Management System (BMS) and automatically controlled for mode...